1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB |
880,000.00 |
2. SUPERSTRUCTURE |
220,000.00 |
3. WALLING |
220,000.00 |
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) |
220,000.00 |
5.WINDOWS |
220,000.00 |
6. DOORS |
220,000.00 |
7. INTERNAL FINISHES |
880,000.00 |
8. EXTERNAL FINISHES |
220,000.00 |
9. FITTING AND FIXTURES (JOINERY) |
220,000.00 |
10. MATERIALS FOR SANITARY APPLIANCES |
440,000.00 |
11. PROVISIONAL WORKS AND PRIME COSTS |
660,000.00 |
|
|
TOTAL |
4,400,000.00 |
*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.
1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB |
929,280.00 |
2. SUPERSTRUCTURE |
232,320.00 |
3. WALLING |
232,320.00 |
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) |
232,320.00 |
5.WINDOWS |
348,480.00 |
6. DOORS |
348,480.00 |
7. INTERNAL FINISHES |
1,452,000.00 |
8. EXTERNAL FINISHES |
290,400.00 |
9. FITTING AND FIXTURES (JOINERY) |
290,400.00 |
10. MATERIALS FOR SANITARY APPLIANCES |
580,800.00 |
11. PROVISIONAL WORKS AND PRIME COSTS |
871,200.00 |
|
|
TOTAL |
5,808,000.00 |
*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)
1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB |
1,126,400.00 |
2. SUPERSTRUCTURE |
281,600.00 |
3. WALLING |
281,600.00 |
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) |
281,600.00 |
5.WINDOWS |
422,400.00 |
6. DOORS |
422,400.00 |
7. INTERNAL FINISHES |
1,760,000.00 |
8. EXTERNAL FINISHES |
352,000.00 |
9. FITTING AND FIXTURES (JOINERY) |
352,000.00 |
10. MATERIALS FOR SANITARY APPLIANCES |
704,000.00 |
11. PROVISIONAL WORKS AND PRIME COSTS |
1,056,000.00 |
|
|
TOTAL |
7,040,000.00 |
*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor