1 |
SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) |
1,020,000.00 |
2 |
REINFORCED CONCRETE FRAME |
255,000.00 |
3 |
WALLING |
306,000.00 |
4 |
ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) |
306,000.00 |
5 |
WINDOWS |
255,000.00 |
6 |
DOORS |
204,000.00 |
7 |
INTERNAL FINISHES |
1,275,000.00 |
8 |
EXTERNAL FINISHES |
306,000.00 |
9 |
FITTING AND FIXTURES (JOINERY) |
204,000.00 |
10 |
PROVISIONAL SUM FOR PLUMBING WORKS |
306,000.00 |
11 |
PROVISIONAL SUM FOR ELECTRICAL WORKS |
255,000.00 |
12 |
PROVISIONAL WORKS AND PRIME COSTS |
408,000.00 |
|
|
|
TOTAL |
|
5,100,000.00 |
*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.
1 |
SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) |
1,360,000.00 |
2 |
REINFORCED CONCRETE FRAME |
340,000.00 |
3 |
WALLING |
408,000.00 |
4 |
ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) |
408,000.00 |
5 |
WINDOWS |
340,000.00 |
6 |
DOORS |
272,000.00 |
7 |
INTERNAL FINISHES |
1,700,000.00 |
8 |
EXTERNAL FINISHES |
408,000.00 |
9 |
FITTING AND FIXTURES (JOINERY) |
272,000.00 |
10 |
PROVISIONAL SUM FOR PLUMBING WORKS |
408,000.00 |
11 |
PROVISIONAL SUM FOR ELECTRICAL WORKS |
340,000.00 |
12 |
PROVISIONAL WORKS AND PRIME COSTS |
544,000.00 |
|
|
|
TOTAL |
|
6,800,000.00 |
*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)
1 |
SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) |
1,700,000.00 |
2 |
REINFORCED CONCRETE FRAME |
425,000.00 |
3 |
WALLING |
510,000.00 |
4 |
ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) |
510,000.00 |
5 |
WINDOWS |
425,000.00 |
6 |
DOORS |
340,000.00 |
7 |
INTERNAL FINISHES |
2,125,000.00 |
8 |
EXTERNAL FINISHES |
510,000.00 |
9 |
FITTING AND FIXTURES (JOINERY) |
340,000.00 |
10 |
PROVISIONAL SUM FOR PLUMBING WORKS |
510,000.00 |
11 |
PROVISIONAL SUM FOR ELECTRICAL WORKS |
425,000.00 |
12 |
PROVISIONAL WORKS AND PRIME COSTS |
680,000.00 |
|
|
|
TOTAL |
|
8,500,000.00 |
*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor