Lagos – 3 Bedroom maisonette – ID M305

3 Bedrooms

314 sqm

4.5 bathrooms

1/8 acres

15X30meters

Price range: KSh 35,000.00 through KSh 45,000.00

Price range: KSh 35,000.00 through KSh 45,000.00

BUILDING COST ESTIMATES

No. Description Amount (Ksh)
1 Substructure & Ground Floor Slab (Provisional) 2,009,600.00
2 Reinforced Concrete Frame 502,400.00
3 Walling 602,880.00
4 Roof Structure, Covering and Rainwater Disposal (Provisional) 602,880.00
5 Windows 502,400.00
6 Doors 401,920.00
7 Internal Finishes 2,512,000.00
8 External Finishes 602,880.00
9 Fitting and Fixtures (Joinery) 401,920.00
10 Provisional Sum for Plumbing Works 602,880.00
11 Provisional Sum for Electrical Works 502,400.00
12 Provisional Works and Prime Costs 803,840.00
TOTAL 10,048,000.00

*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.

No. Description Amount (Ksh)
1 Substructure & Ground Floor Slab (Provisional) 2,763,200.00
2 Reinforced Concrete Frame 690,800.00
3 Walling 828,960.00
4 Roof Structure, Covering and Rainwater Disposal (Provisional) 828,960.00
5 Windows 690,800.00
6 Doors 552,640.00
7 Internal Finishes 3,454,000.00
8 External Finishes 828,960.00
9 Fitting and Fixtures (Joinery) 552,640.00
10 Provisional Sum for Plumbing Works 828,960.00
11 Provisional Sum for Electrical Works 690,800.00
12 Provisional Works and Prime Costs 1,105,280.00
TOTAL 13,816,000.00

*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)

No. Description Amount (Ksh)
1 Substructure & Ground Floor Slab (Provisional) 3,516,800.00
2 Reinforced Concrete Frame 879,200.00
3 Walling 1,055,040.00
4 Roof Structure, Covering and Rainwater Disposal (Provisional) 1,055,040.00
5 Windows 879,200.00
6 Doors 703,360.00
7 Internal Finishes 4,396,000.00
8 External Finishes 1,055,040.00
9 Fitting and Fixtures (Joinery) 703,360.00
10 Provisional Sum for Plumbing Works 1,055,040.00
11 Provisional Sum for Electrical Works 879,200.00
12 Provisional Works and Prime Costs 1,406,720.00
TOTAL 17,584,000.00

*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor