BUILDING COST ESTIMATES

No. Description Amount (Ksh)
1 Substructure & Ground Floor Slab (Provisional) 2,880,000.00
2 Reinforced Concrete Frame 720,000.00
3 Walling 864,000.00
4 Roof Structure, Covering and Rainwater Disposal (Provisional) 864,000.00
5 Windows 720,000.00
6 Doors 576,000.00
7 Internal Finishes 3,600,000.00
8 External Finishes 864,000.00
9 Fitting and Fixtures (Joinery) 576,000.00
10 Provisional Sum for Plumbing Works 864,000.00
11 Provisional Sum for Electrical Works 720,000.00
12 Provisional Works and Prime Costs 1,152,000.00
TOTAL 14,400,000.00

*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.

No. Description Amount (Ksh)
1 Substructure & Ground Floor Slab (Provisional) 3,960,000.00
2 Reinforced Concrete Frame 990,000.00
3 Walling 1,188,000.00
4 Roof Structure, Covering and Rainwater Disposal (Provisional) 1,188,000.00
5 Windows 990,000.00
6 Doors 792,000.00
7 Internal Finishes 4,950,000.00
8 External Finishes 1,188,000.00
9 Fitting and Fixtures (Joinery) 792,000.00
10 Provisional Sum for Plumbing Works 1,188,000.00
11 Provisional Sum for Electrical Works 990,000.00
12 Provisional Works and Prime Costs 1,584,000.00
TOTAL 19,800,000.00

*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)

No. Description Amount (Ksh)
1 Substructure & Ground Floor Slab (Provisional) 5,040,000.00
2 Reinforced Concrete Frame 1,260,000.00
3 Walling 1,512,000.00
4 Roof Structure, Covering and Rainwater Disposal (Provisional) 1,512,000.00
5 Windows 1,260,000.00
6 Doors 1,008,000.00
7 Internal Finishes 6,300,000.00
8 External Finishes 1,512,000.00
9 Fitting and Fixtures (Joinery) 1,008,000.00
10 Provisional Sum for Plumbing Works 1,512,000.00
11 Provisional Sum for Electrical Works 1,260,000.00
12 Provisional Works and Prime Costs 2,016,000.00
TOTAL 25,200,000.00

*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor