Kano – 4 Bedroom maisonette – ID M425

4 Bedrooms

284 sqm

4.5 bathrooms

1/8 acres

15x30meters

KSh 35,000.00

KSh 35,000.00

BUILDING COST ESTIMATES

LOW COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 1,817,600.00
2 REINFORCED CONCRETE FRAME 454,400.00
3 WALLING 545,280.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 545,280.00
5 WINDOWS 454,400.00
6 DOORS 363,520.00
7 INTERNAL FINISHES 2,272,000.00
8 EXTERNAL FINISHES 545,280.00
9 FITTING AND FIXTURES (JOINERY) 363,520.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 545,280.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 454,400.00
12 PROVISIONAL WORKS AND PRIME COSTS 727,040.00
TOTAL 9,088,000.00

*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.

MEDIUM COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 2,499,200.00
2 REINFORCED CONCRETE FRAME 624,800.00
3 WALLING 749,760.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 749,760.00
5 WINDOWS 624,800.00
6 DOORS 499,840.00
7 INTERNAL FINISHES 3,124,000.00
8 EXTERNAL FINISHES 749,760.00
9 FITTING AND FIXTURES (JOINERY) 499,840.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 749,760.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 624,800.00
12 PROVISIONAL WORKS AND PRIME COSTS 999,680.00
TOTAL 12,496,000.00

*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)

HIGH COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 3,180,800.00
2 REINFORCED CONCRETE FRAME 795,200.00
3 WALLING 954,240.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 954,240.00
5 WINDOWS 795,200.00
6 DOORS 636,160.00
7 INTERNAL FINISHES 3,976,000.00
8 EXTERNAL FINISHES 954,240.00
9 FITTING AND FIXTURES (JOINERY) 636,160.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 954,240.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 795,200.00
12 PROVISIONAL WORKS AND PRIME COSTS 1,272,320.00
TOTAL 15,904,000.00

*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor