BUILDING COST ESTIMATES

LOW COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 5,504,000.00
2 REINFORCED CONCRETE FRAME 1,376,000.00
3 WALLING 1,651,200.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 1,651,200.00
5 WINDOWS 1,376,000.00
6 DOORS 1,100,800.00
7 INTERNAL FINISHES 6,880,000.00
8 EXTERNAL FINISHES 1,651,200.00
9 FITTING AND FIXTURES (JOINERY) 1,100,800.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 1,651,200.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 1,376,000.00
12 PROVISIONAL WORKS AND PRIME COSTS 2,201,600.00
TOTAL 27,520,000.00

*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.

MEDIUM COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 7,568,000.00
2 REINFORCED CONCRETE FRAME 1,892,000.00
3 WALLING 2,270,400.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 2,270,400.00
5 WINDOWS 1,892,000.00
6 DOORS 1,513,600.00
7 INTERNAL FINISHES 9,460,000.00
8 EXTERNAL FINISHES 2,270,400.00
9 FITTING AND FIXTURES (JOINERY) 1,513,600.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 2,270,400.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 1,892,000.00
12 PROVISIONAL WORKS AND PRIME COSTS 3,027,200.00
TOTAL 37,840,000.00

*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)

LUXURY COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 9,632,000.00
2 REINFORCED CONCRETE FRAME 2,408,000.00
3 WALLING 2,889,600.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 2,889,600.00
5 WINDOWS 2,408,000.00
6 DOORS 1,926,400.00
7 INTERNAL FINISHES 12,040,000.00
8 EXTERNAL FINISHES 2,889,600.00
9 FITTING AND FIXTURES (JOINERY) 1,926,400.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 2,889,600.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 2,408,000.00
12 PROVISIONAL WORKS AND PRIME COSTS 3,852,800.00
TOTAL 48,160,000.00

*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor