BUILDING COST ESTIMATES

LOW COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 1,420,800.00
2 REINFORCED CONCRETE FRAME 355,200.00
3 WALLING 426,240.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 426,240.00
5 WINDOWS 355,200.00
6 DOORS 284,160.00
7 INTERNAL FINISHES 1,776,000.00
8 EXTERNAL FINISHES 426,240.00
9 FITTING AND FIXTURES (JOINERY) 284,160.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 426,240.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 355,200.00
12 PROVISIONAL WORKS AND PRIME COSTS 568,320.00
TOTAL 7,104,000.00

*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.

MEDIUM COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 1,953,600.00
2 REINFORCED CONCRETE FRAME 488,400.00
3 WALLING 586,080.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 586,080.00
5 WINDOWS 488,400.00
6 DOORS 390,720.00
7 INTERNAL FINISHES 2,442,000.00
8 EXTERNAL FINISHES 586,080.00
9 FITTING AND FIXTURES (JOINERY) 390,720.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 586,080.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 488,400.00
12 PROVISIONAL WORKS AND PRIME COSTS 781,440.00
TOTAL 9,768,000.00

*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)

HIGH COST
No. Description Amount (KES)
1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 2,486,400.00
2 REINFORCED CONCRETE FRAME 621,600.00
3 WALLING 745,920.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 745,920.00
5 WINDOWS 621,600.00
6 DOORS 497,280.00
7 INTERNAL FINISHES 3,108,000.00
8 EXTERNAL FINISHES 745,920.00
9 FITTING AND FIXTURES (JOINERY) 497,280.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 745,920.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 621,600.00
12 PROVISIONAL WORKS AND PRIME COSTS 994,560.00
TOTAL 12,432,000.00

*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor