4 Bedrooms
226 sqm
4.5 bathrooms
1/8 acres
15X30meters
KSh 35,000.00 – KSh 45,000.00Price range: KSh 35,000.00 through KSh 45,000.00
KSh 35,000.00 – KSh 45,000.00Price range: KSh 35,000.00 through KSh 45,000.00
| LOW COST | ||
|---|---|---|
| No. | DESCRIPTION | AMOUNT (KES) |
| 1 | SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) | 1,446,400.00 |
| 2 | REINFORCED CONCRETE FRAME | 361,600.00 |
| 3 | WALLING | 433,920.00 |
| 4 | ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) | 433,920.00 |
| 5 | WINDOWS | 361,600.00 |
| 6 | DOORS | 289,280.00 |
| 7 | INTERNAL FINISHES | 1,808,000.00 |
| 8 | EXTERNAL FINISHES | 433,920.00 |
| 9 | FITTING AND FIXTURES (JOINERY) | 289,280.00 |
| 10 | PROVISIONAL SUM FOR PLUMBING WORKS | 433,920.00 |
| 11 | PROVISIONAL SUM FOR ELECTRICAL WORKS | 361,600.00 |
| 12 | PROVISIONAL WORKS AND PRIME COSTS | 578,560.00 |
| TOTAL | 7,232,000.00 | |
| MEDIUM COST | ||
|---|---|---|
| No. | DESCRIPTION | AMOUNT (KES) |
| 1 | SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) | 1,988,800.00 |
| 2 | REINFORCED CONCRETE FRAME | 497,200.00 |
| 3 | WALLING | 596,640.00 |
| 4 | ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) | 596,640.00 |
| 5 | WINDOWS | 497,200.00 |
| 6 | DOORS | 397,760.00 |
| 7 | INTERNAL FINISHES | 2,486,000.00 |
| 8 | EXTERNAL FINISHES | 596,640.00 |
| 9 | FITTING AND FIXTURES (JOINERY) | 397,760.00 |
| 10 | PROVISIONAL SUM FOR PLUMBING WORKS | 596,640.00 |
| 11 | PROVISIONAL SUM FOR ELECTRICAL WORKS | 497,200.00 |
| 12 | PROVISIONAL WORKS AND PRIME COSTS | 795,520.00 |
| TOTAL | 9,944,000.00 | |
| LUXURY COST | ||
|---|---|---|
| No. | DESCRIPTION | AMOUNT (KES) |
| 1 | SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) | 2,531,200.00 |
| 2 | REINFORCED CONCRETE FRAME | 632,800.00 |
| 3 | WALLING | 759,360.00 |
| 4 | ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) | 759,360.00 |
| 5 | WINDOWS | 632,800.00 |
| 6 | DOORS | 506,240.00 |
| 7 | INTERNAL FINISHES | 3,164,000.00 |
| 8 | EXTERNAL FINISHES | 759,360.00 |
| 9 | FITTING AND FIXTURES (JOINERY) | 506,240.00 |
| 10 | PROVISIONAL SUM FOR PLUMBING WORKS | 759,360.00 |
| 11 | PROVISIONAL SUM FOR ELECTRICAL WORKS | 632,800.00 |
| 12 | PROVISIONAL WORKS AND PRIME COSTS | 1,012,480.00 |
| TOTAL | 12,656,000.00 | |