PLANNING

ROOF PLAN

GROUND FLOOR

FIRST FLOOR

Share:

Kampala- 4 Bedroom Maisonette- ID M413

4 Bedrooms

330 sqm

3.0 bathrooms

1/8 acres

15x30meters

BUILDING COST ESTIMATES

1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 2,112,000.00
2 REINFORCED CONCRETE FRAME 528,000.00
3 WALLING 633,600.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 633,600.00
5 WINDOWS 528,000.00
6 DOORS 422,400.00
7 INTERNAL FINISHES 2,640,000.00
8 EXTERNAL FINISHES 633,600.00
9 FITTING AND FIXTURES (JOINERY) 422,400.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 633,600.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 528,000.00
12 PROVISIONAL WORKS AND PRIME COSTS 844,800.00
TOTAL 10,560,000.00

*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.

1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 2,904,000.00
2 REINFORCED CONCRETE FRAME 726,000.00
3 WALLING 871,200.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 871,200.00
5 WINDOWS 726,000.00
6 DOORS 580,800.00
7 INTERNAL FINISHES 3,630,000.00
8 EXTERNAL FINISHES 871,200.00
9 FITTING AND FIXTURES (JOINERY) 580,800.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 871,200.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 726,000.00
12 PROVISIONAL WORKS AND PRIME COSTS 1,161,600.00
TOTAL 11,664,000.00

*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)

1 SUBSTRUCTURE & GROUND FLOOR SLAB (PROVISIONAL) 3,696,000.00
2 REINFORCED CONCRETE FRAME 924,000.00
3 WALLING 1,108,800.00
4 ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL (PROVISIONAL) 1,108,800.00
5 WINDOWS 924,000.00
6 DOORS 739,200.00
7 INTERNAL FINISHES 4,620,000.00
8 EXTERNAL FINISHES 1,108,800.00
9 FITTING AND FIXTURES (JOINERY) 739,200.00
10 PROVISIONAL SUM FOR PLUMBING WORKS 1,108,800.00
11 PROVISIONAL SUM FOR ELECTRICAL WORKS 924,000.00
12 PROVISIONAL WORKS AND PRIME COSTS 1,478,400.00
TOTAL 18,480,000.00

*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor