BUILDING COST ESTIMATES

1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB 625,000.00
2. SUPERSTRUCTURE 156,250.00
3. WALLING 156,250.00
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) 156,250.00
5.WINDOWS 156,250.00
6. DOORS 156,250.00
7. INTERNAL FINISHES 625,000.00
8. EXTERNAL FINISHES 156,250.00
9. FITTING AND FIXTURES (JOINERY) 156,250.00
10. MATERIALS FOR SANITARY APPLIANCES 312,500.00
11. PROVISIONAL WORKS AND PRIME COSTS 468,750.00
TOTAL 3,125,000.00

*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.

1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB 660,000.00
2. SUPERSTRUCTURE 165,000.00
3. WALLING 165,000.00
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) 165,000.00
5.WINDOWS 247,500.00
6. DOORS 247,500.00
7. INTERNAL FINISHES 1,031,250.00
8. EXTERNAL FINISHES 206,250.00
9. FITTING AND FIXTURES (JOINERY) 206,250.00
10. MATERIALS FOR SANITARY APPLIANCES 412,500.00
11. PROVISIONAL WORKS AND PRIME COSTS 618,750.00
TOTAL 4,125,000.00

*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)

1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB 800,000.00
2. SUPERSTRUCTURE 200,000.00
3. WALLING 200,000.00
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) 200,000.00
5.WINDOWS 300,000.00
6. DOORS 300,000.00
7. INTERNAL FINISHES 1,250,000.00
8. EXTERNAL FINISHES 250,000.00
9. FITTING AND FIXTURES (JOINERY) 250,000.00
10. MATERIALS FOR SANITARY APPLIANCES 500,000.00
11. PROVISIONAL WORKS AND PRIME COSTS 750,000.00
TOTAL 5,000,000.00

*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor