1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB |
625,000.00 |
2. SUPERSTRUCTURE |
156,250.00 |
3. WALLING |
156,250.00 |
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) |
156,250.00 |
5.WINDOWS |
156,250.00 |
6. DOORS |
156,250.00 |
7. INTERNAL FINISHES |
625,000.00 |
8. EXTERNAL FINISHES |
156,250.00 |
9. FITTING AND FIXTURES (JOINERY) |
156,250.00 |
10. MATERIALS FOR SANITARY APPLIANCES |
312,500.00 |
11. PROVISIONAL WORKS AND PRIME COSTS |
468,750.00 |
|
|
TOTAL |
3,125,000.00 |
*Low Cost assumes construction in rural areas with low labor rates on a labor contract with budget finishes.
1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB |
660,000.00 |
2. SUPERSTRUCTURE |
165,000.00 |
3. WALLING |
165,000.00 |
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) |
165,000.00 |
5.WINDOWS |
247,500.00 |
6. DOORS |
247,500.00 |
7. INTERNAL FINISHES |
1,031,250.00 |
8. EXTERNAL FINISHES |
206,250.00 |
9. FITTING AND FIXTURES (JOINERY) |
206,250.00 |
10. MATERIALS FOR SANITARY APPLIANCES |
412,500.00 |
11. PROVISIONAL WORKS AND PRIME COSTS |
618,750.00 |
|
|
TOTAL |
4,125,000.00 |
*Medium assumes construction in a periurban area with moderate labour costs, average finishes and a hybrid contract( part labour)
1. SUBSTRUCTURE (ALL PROVISIONAL) & GROUND FLOOR SLAB |
800,000.00 |
2. SUPERSTRUCTURE |
200,000.00 |
3. WALLING |
200,000.00 |
4. ROOF STRUCTURE, COVERING AND RAINWATER DISPOSAL ( PROVISIONAL ) |
200,000.00 |
5.WINDOWS |
300,000.00 |
6. DOORS |
300,000.00 |
7. INTERNAL FINISHES |
1,250,000.00 |
8. EXTERNAL FINISHES |
250,000.00 |
9. FITTING AND FIXTURES (JOINERY) |
250,000.00 |
10. MATERIALS FOR SANITARY APPLIANCES |
500,000.00 |
11. PROVISIONAL WORKS AND PRIME COSTS |
750,000.00 |
|
|
TOTAL |
5,000,000.00 |
*Luxury assumes construction in an urban area with high labour costs, high end finishes with a full contract engagement with the contractor